Development of Data Center Valley in Ekibastuz will be planned around Kazakhstan’s electricity supply and demand, the Ministry of Artificial Intelligence and Digital Development said (t.me). The country plans to add more than 13 GW of new power generation capacity by 2030. The government will oversee delivery of the energy projects.
More than 13 GW of new capacity planned nationwide
Deputy Prime Minister and Minister of Artificial Intelligence and Digital Development Zhaslan Madiyev linked the valley’s development to Kazakhstan’s power supply planning (rus.baq.kz). He said the government is tracking progress on energy projects and expects the plans to be delivered.
There’s an important detail here: the more than 13 GW refers to new capacity across Kazakhstan. The ministry cites the nationwide plan in connection with the valley’s development.
Customers have reserved the first phase’s 215 MW
According to the digital ministry, the first phase’s entire 215 MW of capacity has already been reserved (kz.kursiv.media). Bagdat Mussin also said the first phase has customers lined up and the project has firm investment commitments.
Madiyev is calling for work to start now on building relationships with global IT companies. He named Nvidia, Amazon, Google and Meta among those Kazakhstan wants to attract. The aim is to host cloud infrastructure and find customers for GPU computing capacity.
A 200-hectare site selected near GRES-1
A 200-hectare site near Ekibastuz GRES-1 has been selected for the special zone (primeminister.kz). The area could eventually expand to more than 1,300 hectares.
Plans for the site include 15 km of power lines and step-down substations with a capacity of 300 MW. The substations’ capacity is expected to expand to 1 GW in the future. The project also includes 500 new highly skilled jobs, including in energy and the operation of computing facilities.
First facility scheduled to launch in June 2027
Madiyev said the valley’s first facility is scheduled to launch in June 2027. The government will also discuss support for social infrastructure in Ekibastuz and Pavlodar Region with investors. Madiyev linked this task to the valley’s use of the region’s resources.
raem.kz previously reported on plans to launch three data centers with a combined capacity of 304 MW in 2027. The project’s capacity is expected to reach 1 GW by 2029.
On November 20, raem.kz reported that DBK had approved 50 billion tenge for Data Center Valley. The project costs 236.8 billion tenge.