Businesses given one-year utility connection specifications get the required three years in Zhambyl Region

A documentary photograph of an employee at an industrial site in Zhanatas, Zhambyl Region, with pipelines in the background and no text.

Photo: shymkent xu / Pexels

EuroChem and 26 other entrepreneurs in Zhambyl Region have had their technical specifications for utility connections reissued with a three-year validity period instead of one year. The utility had shortened the documents’ validity without justification, Kursiv reports (kursiv.media). According to the regional prosecutor’s office, businesses had to reapply every year. The process took up to 15 calendar days.

Why businesses had to renew their technical specifications every year

The municipal utility Zhanatas-Su-Zhylu issued technical specifications valid for one year instead of the required three. The Sarysu District prosecutor’s office uncovered the violation while reviewing the operations of natural monopolies.

Among the recipients was EuroChem, which is developing a mineral fertilizer production project. It had been receiving technical specifications with a shortened validity period since 2023.

Which connections the documents covered

EuroChem’s technical specifications covered connections to three utility systems:

  • water supply;
  • heating;
  • wastewater disposal.

The violation also affected 26 entrepreneurs in addition to the investor. Their documents were also reissued after prosecutors intervened.

How long the renewal process took

Businesses spent up to 15 calendar days renewing their technical specifications. With the documents valid for only one year, entrepreneurs had to go through the process repeatedly.

The prosecutor’s office found that the shortened validity period was unjustified: in this case, the technical specifications should have been valid for three years.

How prosecutors secured the reissued documents

Following the prosecutors’ intervention, the investor and the entrepreneurs received technical specifications with the corrected validity period.

“Following the prosecutors’ intervention, the technical specifications for the investor and 26 entrepreneurs were reissued for a three-year term,” the prosecutor’s office said.

The official responsible for the violation faced disciplinary action.

What project EuroChem is developing in Zhambyl Region

The group mines and processes phosphate rock in the region. In May 2026, it launched a sulfuric acid plant with a design capacity of 800 thousand tonnes a year.

Total investment in the project exceeds $1 billion. The next phase is scheduled for 2027: the launch of a complex producing fertilizers and industrial chemicals.

Понравился материал? Поделитесь с другими:

Picture of Раимбек Искендиров
Раимбек Искендиров
Picture of Раимбек Искендиров
Раимбек Искендиров

Похожие материалы

An operator with a remote controller and a civilian drone at an outdoor site in Kazakhstan, showing a real person in a real setting, with no text.

Обзоры

Bektenov approves Kazakhstan’s unmanned systems development plan through 2029

Unmanned systems in Kazakhstan get a 2026–2029 development plan approved by Bektenov, with deadlines ...
A customer speaks with an adviser at a desk in an Otbasy Bank branch in Kazakhstan. A candid, everyday scene with no text or legible personal information.

Обзоры

Otbasy Bank loans: how much will the fee be from October 31?

Otbasy Bank will change fee caps for preliminary and interim loans from October 31. ...
A person checks their phone at the entrance to a street-side currency exchange office in Almaty. Documentary photograph in natural light, with no text, logos or readable numbers.

Обзоры

Buying dollars in Kazakhstan: which rate to check for October 24–27

Dollar exchange rate for October 24–27: 451.05 tenge officially. Check rates in the capital ...

Читайте нас в Telegram и Instagram

Подписывайтесь на наши каналы, чтобы первыми получать самые свежие новости казахстанской IT-индустрии, анонсы грантов, стажировок и эксклюзивные интервью.