Gcore and Kazakhstan’s TengriAI have signed a memorandum to study building an AI data center of up to 100 MW (the-tech.kz). The plan is to build it in phases from 2027 to 2029. Companies in Central Asia would no longer have to rent GPU capacity outside the region.
So far only a memorandum has been signed. It records an intention to study the project.
TengriAI builds, Gcore runs the cloud and brings in clients
The roles are split. TengriAI is responsible for the land plot, the grid connection, the permits and the construction itself.
Gcore provides the cloud AI platform, takes over operations and brings in clients from its international network. According to the company’s press release (gcore.com), the platform is the same as in Gcore’s own GPU clouds. It was built together with NVIDIA, where Gcore is a Preferred Cloud Partner.
The site will be managed from Kazakhstan, and clients will be served across the whole region.
Data stays on site
Users will be able to run isolated computing workloads without sending data outside the data center. The capacity can be resold, and usage can be tracked and paid for right on the platform.
GPUs, or graphics processors, are needed to train AI models and put them to work. That is what the center is designed for.
Gcore says the project should let regional organizations run AI in the jurisdiction their regulators require, rather than abroad.
Right now, computing is rented in Europe, the Middle East or Asia
Companies in the region often use infrastructure in Europe, the Gulf states or East Asia. Gcore adds that this capacity is often far away and sometimes sits outside the jurisdictions regulators require.
The company estimates that Central Asia’s digital economy is growing fast, while its own AI capacity is small. Large projects are underway in Kazakhstan and Uzbekistan.
Gcore CEO Andre Reitenbach says: “Every market we work in asks one question: how do we run AI on our own terms?” He adds: “Kazakhstan has the energy and the intention to answer it.”
Why Kazakhstan
Gcore’s release lists the reasons: cheap energy, available industrial land, a climate that cuts cooling costs, the state’s priority on AI infrastructure and a location between Europe and Asia. It also names the common-law regime of the Astana International Financial Centre.
TengriAI CEO Nurassyl Medeu puts the goal this way: “To make Kazakhstan the leading AI token hub in Central Asia.” TengriAI itself builds “AI factories”, which combine energy infrastructure, computing resources and AI services.
Nearby: Firebird’s 1 GW in Ekibastuz
This is not the only big project. In June, Kazakhstan signed agreements worth €8.6 billion with the AI company Firebird, backed by NVIDIA (euronews.com). It is a 1 GW “Data Center Valley” in Ekibastuz. Almost €26 billion in total investment is expected from global tech companies.
For scale: the 100 MW from Gcore and TengriAI is one tenth of 1 GW.
Firebird signed a binding term sheet with Kazakhtelecom. Firebird head Razmig Hovaghimian said that a 2027 launch could put Kazakhstan among the world’s top ten countries in this field. By his account, even 100 MW of computing capacity could bring billions of euros in economic returns.
Deputy Prime Minister Zhaslan Madiyev named the country’s advantages: low energy prices, international connectivity, tax breaks and simplified procedures for large investment projects. Prime Minister Olzhas Bektenov said the goal is to “create a platform for hosting global digital infrastructure.”
To read about AI development in the country at other levels, see the story of Yerzat Dulat’s path to an AI unicorn and the Ustaz AI service for teachers.
No amount and no date for a final agreement yet
Gcore’s release gives neither a date for the final agreement nor the investment amount. All we know is the 100 MW target and the 2027–2029 timeline. The construction site hasn’t been named either.
Gcore lists Orange, Wargaming, Xsolla and Avast among its clients. TengriAI develops AI infrastructure, data centers and GPU computing.