A hurdle to building Zijin Mining’s gold processing plant in the Akmola region, backed by more than $600 million in foreign investment, has been removed. Lengthy environmental procedures could have delayed preparatory work until April 2027 and pushed back the construction schedule (inbusiness.kz).
What happened
International mining company Zijin Mining plans to build a plant designed to process 10 million tonnes of ore a year. The plant will extract gold from the ore.
Preparations for the project faced possible delays because of lengthy environmental procedures. Postponing the start of work until April 2027 could also have affected the rest of the construction schedule.
The Akmola regional prosecutor’s office stepped in. At its initiative, the responsible authority decided to use a simplified environmental review procedure without requiring an environmental impact assessment.
What this means
The decision removes a procedural hurdle that threatened to delay project preparations. One detail matters here: the simplified procedure applies to the environmental review before the plant is built.
The future plant is expected to create jobs and increase tax revenue. The prosecutor’s office also expects the project to strengthen Kazakhstan’s industrial capacity.
For now, the project is still at the stage of preparing for construction. The stated 10 million tonnes a year is the future plant’s design capacity, while April 2027 was the possible postponed start date for preparatory work.